New Steel Roof
|
 |
|
|
|
|
|
|
|
|
|
|
|
It's Naked !!
|
|
It took about 6 hours per side, 18 feet by 34 feet, to strip the shingles. Then it took my wife about the same amount of time to move the rubble to the burn pile, thats as far from the barn as you can get.
So about 24 person hours to strip and clean up.
Now we get to install the 2 x 4 purlins. To make the 32 foot width we decided to go with an 8 foot 2x4 in the center and 14 foot 2x4's on each side, overhanging the gable end. We will snap a chalkline once all of this is installed and trim the purlins to length.
|
|
|
|
|
|
|
|
|
All projects on Shareaproject.com are user-submitted and should be used for reference information only. The projects are not intended to be complete "How-To" articles. Use the information contained in these projects at your own risk. Projects are not checked for completion, accuracy, or safety and therefore cannot be guaranteed in any way.
Outdoor Blog
|